Nov, 03, 2022

Conceptual Approval at Historic Design Review

Gold Key Builders presented for conceptual review at the Ohio City Historic Design Review meeting on November 3rd 2022. View the meeting here: https://www.youtube.com/watch?v=IywbxEZv9wQ&t=86s

Nov, 15, 2022

November Community Meeting

Gold Key Builders will present on November 15th at the Ohio City Community Meeting. To learn more about the next community meeting, visit: http://www.ohiocity.org/community-meetings

Dec, 01, 2022

Conceptual Review at Ohio City Historic Design Review

The updated project plan will be conceptually reviewed at the December 1st Ohio City Design Review meeting. For more info, please visit: http://www.ohiocity.org/local-historic-design-review

Jan, 12, 2023

Landmarks Conceptual Review

This project was reviewed conceptually at Landmarks Commission on January 12th, 2023. Watch here: https://www.youtube.com/watch?v=L-0tT7C5qFk

March 2nd, 2023

Ohio City Design Review meeting

This project will be presented for final approval at the upcoming Ohio City Design Review meeting on March 2nd, 2023.

Meeting presentation

March 9th, 2023

Landmarks Commission Meeting

This project will go back to the Landmarks Commission for final approval on March 9th, 2023.

Meeting Presentation

March 16th, 2023

Design Review Meeting

Presenting for final approval at the Ohio City Design Review meeting

July 3rd, 2023

BZA Meeting

The variances needed to proceed were approved at Board of Zoning Appeals on July 3rd, 2023.

Summer 2023

Permitting Process Begins

Plan reviews will be submitted to the city. Plan reviews typically take 30-45 days.

Estimated January 2024

Groundbreaking

A groundbreaking on 2 of the 5 homes is expected to take place upon approval of the building permits. Subscribe for updates on the groundbreaking!